There will be crews on site this Saturday, March 12, at the St. Lawrence Condominiums. Crews will be working on[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
There will be crews on site this Saturday, March 12, at the St. Lawrence Condominiums. Crews will be working on[…]
Read moreThere will be a crew working on the site this Saturday, March 5. They will be doing a mix of[…]
Read moreThere will be a normal crew on Saturday, February 26 doing site housekeeping work, preparations for next week, and ongoing[…]
Read moreThere will be no work on the site this Saturday, February 19. The site will also be closed on Monday,[…]
Read moreOn Wednesday, February 16, the process of removing the shoring along the Front Street East section of the site will[…]
Read moreThere will be a mobile crane deployed on Front Street East tomorrow to remove the last section of the West[…]
Read moreInterior finishing is ongoing throughout the building. Lobby finishing is ongoing on the main floor. The West Tower Hoist (external[…]
Read moreThe new sidewalk on the Frederick Street side of the building has been poured. The sidewalk will have a new[…]
Read moreWork continues this week on suite finishing throughout the upper floors of the building. Deliveries will continue throughout the week.[…]
Read moreThe West Tower Hoist (external construction elevator) removal got underway today, Monday, January 24. The removal of the Hoist is[…]
Read more