The main focus of work at 158 Front Street East continues to be the remaking of the Front Street Sidewalk[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
The main focus of work at 158 Front Street East continues to be the remaking of the Front Street Sidewalk[…]
Read moreAs the St. Lawrence Condominiums at 158 Front Street East come closer to being completed, we note that a substantial[…]
Read moreThere will be a concrete truck on-site tomorrow as part of the ongoing sidewalk reconstruction. We do not have the[…]
Read moreThere will be a small work crew on site, Saturday, April 30, They will be working on the fins on[…]
Read moreWork continues to progress on the Front Street East frontage of the St. Lawrence Condominiums. Current work is focused on[…]
Read moreWork continues this week on Front Street East to remove the old sidewalk and the remnants of the shoring that[…]
Read moreThere will be a crew on site tomorrow, Saturday, April 9, conducting a variety of tasks throughout the building and[…]
Read moreMobile Crane on Front St. April 1 A mobile crane will be deployed on Friday, April 1, to remove the[…]
Read moreWork crews will be on site this Saturday, March 26 doing a number of housekeeping and interior tasks throughout the[…]
Read moreThis week work will focus on completing the shoring removal process along Front Street. If that goes well and the[…]
Read more