Work will continue on the Front Street East sidewalk for the coming week. Interlocking brick is being installed along the northern portion of the sidewalk area.

A concrete pour on the eastern half of the Front Street sidewalk is expected next week.
Work on the Frederick Street sidewalk is substantially complete, as is the Sherbourne Street sidewalk north of Front Street East.



Work continues on the interior of the building focussing on finishes to the upper floor suites and hallways.
Some remaining exterior finishing remains to be completed and work on these areas will continue through the balance of the month.