Mid-Week Construction Update.

Work continues to progress on the Front Street East frontage of the St. Lawrence Condominiums. Current work is focused on the all preparation of the ground for forming and pouring the new concrete sidewalk, which will occur later in the spring.

Some of this work is unavoidably noisy, such as the hydro-vac that is in use this week, clearing out the areas where the street lights will be reinstalled.

After the successful installation of precast cladding on the East Tower, this past Saturday, workers are installing the remaining windows, cleaning up areas of the site, working on the interior of the remaining upper floor and East Tower suites that are not yet finished.

We do not expect there to be work on site this coming weekend. However, we will post an update if the work schedule changes.