Work continues this week on Front Street East to remove the old sidewalk and the remnants of the shoring that was installed at the very beginning of construction.
There will be ongoing deliveries of supplies and materials as work to finish the upper floor suites continues. Finished suites are being inspected prior to occupancy later this spring.
Saturday, April 23 Mobile Crane on Front Street East
There will be a mobile crane deployed on Front Street East occupying a lane. The crane will be used to install precast panels on the face of the East Tower where the hoist (external construction elevator) used to be located. There will be a Paid Duty Officer on site during the operation, as well as on-site traffic control staff. The work is expected to take no more than one day.