This week work will focus on completing the shoring removal process along Front Street. If that goes well and the weather cooperates, the removal of the existing Front Street sidewalk may get underway late this week or early next week, the week of March 23.

Other exterior work will be focused on two main fronts: 1) Continuing to install glass (glazing) along the ground floor facades; 2) Disassembling the East Tower Hoist (external construction elevator).

Interior work continues throughout the building with an emphasis on the upper floors of the East and West towers, and the suites that were adjacent to the West Tower Hoist. There will be regular deliveries of material and supplies to support the interior suite finishing.

Saturday March 19
A crew will be on site on Saturday, March 19, working on a variety of tasks throughout the building.
NOTE: Our next scheduled update will be posted on Wednesday March 23. If there are any major changes to the construction schedule, we will post an interim update.