There will be a crew working on the site this Saturday, March 5. They will be doing a mix of interior finishing work and housekeeping across the site.
The new Sherbourne Street sidewalk was poured and finished, this past week. Both the east and west sidewalks adjacent to the building have now been completed.

The work to remove the shoring on the Front Street East frontage continues through the coming week. This is the first step in the reconstruction of the Front Street sidewalk.
Interior work and associated deliveries will be ongoing through the coming week.
On Monday, March 7, the work will begin to dismantle the East Tower Hoist (external construction elevator). This work will take approximately one month.