Frederick Street Sidewalk poured at 158 Front St. E.

The new sidewalk on the Frederick Street side of the building has been poured. The sidewalk will have a new tree planted in the coming months.

New Frederick Street sidewalk.

On Sherbourne Street the removal of the old sidewalk concrete remains underway.

As we have noted in the previous updates, deliveries and material movement is ongoing as the interior suite finishing work continues throughout the upper floors of the west and east towers.

Once we have information on the deployment of a mobile crane to remove the lower sections of the west tower hoist (external construction elevator) we will provide it.

As per the standard pattern of work at 158 Front Street East, we expect that there will be a crew on site this coming Saturday, February 5.