For the first week of the New Year, crews at 158 Front Street East will be preparing to pour the new concrete sidewalk on Frederick Street. Weather will be a factor of course at this time of year, so delays may occur if it is too cold to pour concrete.
On the east side of the site, shoring removal is ongoing along the Sherbourne Street frontage. As a reminder, the Bike Lane, per City of Toronto permit approvals, will remain closed during the shoring removal and sidewalk reconstruction.
Also on the schedule for this week: the roll up overhead door installation is set to take place; along with ongoing typical drywall, kitchen and appliance installation throughout the interior of the building.
We expect a normal Saturday schedule for January 8, 2022: crews on site doing interior work, general housekeeping and related tasks.
Sherbourne Street Shoring Removal Area