Holiday Construction Schedule for 158 Front St. E.

The site will be open on the days indicated below through the holidays. This will be our final regular post of 2021. Our next regular post will be on January 3, 2022, unless there is a significant change to the construction schedule. As we’ve reported previously, the main focus of exterior work at the site is on the shoring removal and sidewalk work on Frederick Street and Sherbourne Street. The main focus of interior work is ongoing suite finishing throughout the building. 

We hope you have a safe and Happy Holiday Season. Please accept our best wishes for the New Year. 

Here is the Holiday Construction Work Schedule for the St. Lawrence Condominiums at 158 Front Street East:

Dec 20th – 23rd – Full Working Day

Dec 24th – Christmas Eve – ½ day

Dec 25th – Christmas Day – Closed

Dec 26th – Boxing Day – Closed

Dec 27th – Closed

Dec 28th – Closed

Dec 29th – Full Working Day

Dec 30th – Full Working Day

Dec 31st – New Year’s Eve – ½ day

January 1st – New Year’s Day – Closed


Focus of Work on Site on Working Days:


Shoring removal on Sherbourne Street is on-going. 

One Fredrick Street the silva cells for the new street trees were insulated last week. In the coming days work will focus on preparing for the installation of the new sidewalk

Inside the building kitchens, tiles and flooring are progressing on multiple floors.  