Shoring removal on Sherbourne Street is underway and will continue through the coming week. 

Sidewalk removal on Frederick Street is also ongoing.

Once the existing sidewalk is removed on Frederick Street, construction of the new sidewalk will begin. Similarly on Sherbourne Street, once shoring removal is complete, sidewalk removal will get underway. Then the new Sherbourne Street sidewalk will be constructed.

Work on the Front Street sidewalk will follow Frederick Street and Sherbourne Street.

Saturday, December 11

There will be a crew on site this Saturday doing housekeeping work and interior work.

Other areas of focus

Inside the building the interior finishes, flooring, kitchen, and tile installations are continuing to progress.

Deliveries to the main gates on Front Street will be ongoing throughout the coming week.

The driveway that leads off Frederick Street is close to completion.