The site crew at 158 Front Street East will be completing shoring removal on Frederick Street today.
Shoring removal crews will then move to Sherbourne Street on Monday, November 29, and start removal on the east side of the site.
Sherbourne Street Shoring Removal & Sidewalk Reconstruction Plan
By the end of the coming week or the beginning of the week of December 6th, work crews will start removing the rest of the remaining (old) sidewalk on Frederick Street. Sidewalk removal on Frederick Street is planned to commence in approximately one week, again between December 3rd and 7th. NOTE: Sidewalk reconstruction on Frederick Street and shoring removal on Sherbourne Street will be happening at the same time.
Deliveries to the site and hauling waste material from the site will continue through the week of November 29th.
Interior suite finishing continues progressing to the higher floors of the building.
The paving of the driveway off Frederick Street will also continue through the coming week.