Work at 158 Front Street East continues to be focussed on finishing interiors, completing the remaining exterior finishes and glazing, and the removal of shoring on Frederick Street, in advance of sidewalk reconstruction.
Saturday, November 13
There will be a crew on site this Saturday focused on general housekeeping and clean up work.
The Week of November 15
Shoring removal on Frederick Street will continue through most of next week.
Landscape pavers are being installed in the driveway the runs on the north side of the building, off Frederick Street.
Sidewalk reconstruction on Frederick Street is set to commence towards the end of next week or beginning of the following week, Nov 22nd and onwards.