Contractors will continue with shoring removal on Frederick Street this upcoming week. This is the first step in the sidewalk rebuilding work that will deliver a new sidewalk on Frederick Street.
We expect a small crew to be on site this Saturday, October 22 doing a variety of tasks throughout the site. Activities that generate construction noise will not get underway until 9 am.
Next week crews will commence paving stone installation on the driveway that connects to Frederick Street. All paving stone work will occur within site.
Suite framing, drywall work, painting and related suite finishing tasks are ongoing throughout the building.
Fin installation is ongoing on the north east side of the building; as well 23rd floor canopy cladding application is underway.