Construction Update for 158 Front Street East

Work continues to progress at the St. Lawrence Condominiums.

The windows for the whole of the west tower should be completed this week. 

The window completion on the east tower should be complete by the end of next week. 

Brick work continues on the ground floor to be completed in 2 ½ weeks weather permitting.

Suite metal framing is currently ongoing on the 22nd to 23rd  floor, drywall is being installed on the 18th to 19th floors, kitchen installation is underway on the 13th floor, and flooring is being installed on the 9th and 10th floors. 

Looking Ahead

Sidewalk and shoring removal on Frederick Street will tentatively get underway the week of October 1st. We will be providing more details on this work in our next update.