As work progresses toward the completion of the St. Lawrence Condominiums, there is still much to do. The balance of September will be a busy time at 158 Front Street East.
The site will be closed for the Labour Day Holiday. Work will resume on Tuesday, September 7th.
Currently suite framing is active and continuing on the 21st floor. Drywall work is ongoing on the 17th floor. Suite taping is underway on the 14th floor. Terrace work is ongoing.
September Highlights:
The construction team expects to complete window installation by the middle of the month.
Ground floor brick work to be completed by late September.
Back alley interlock paving stone installation is excepted to commence by the end of September.
Between the end of the month and the beginning of October, an excavation crew will be onsite to commence the pile and sidewalk removal on Frederick Street.
NOTE: Frederick Street sidewalk reconstruction will get underway after this work is completed but we have no specific start time for that phase of work at this time.