Saturday Work and Construction Outlook for 158 Front Street East.

Crews will be on site Saturday, August 14. They will be conducting miscellaneous work throughout the site.  

Work over the next week and for the balance of August will be constant but mostly focused on the interior of the building and the completion of the exterior glazing (window installation).

The installation of the ground floor curtain wall windows has commenced and will continue until it is completed. This will begin to a give a sense of the finished look of the building at street level.

In a week, weather permitting, the ground floor brick work is set to commence.

We anticipate no major work impacting traffic flows or pedestrian movement around the site.

If there are significant changes to the construction schedule we will post and circulate the details.