Currently and through next week mechanical penthouse cladding is being installed on the West and East towers.
Window installation is ongoing on the 23rd floor.
Interior Work
Elevator installation is underway for both the East and West tower elevator shafts. Corridor framing is ongoing on the 20th floor. 18th floor suite framing is in progress. Drywall installation has reached the 13th floor. Kitchen install is getting started on the 9th floor. Suites on the 7thfloor are currently being painted.
Saturday Work
We expect there to be light crew on site this Saturday and next Saturday, they will be continuing with windows, interior work and general housekeeping.