Ongoing work at 158 Front Street East

In addition to the crane removal planned for July 9 – 11 (details of which are posted here – click to read) work is continuing throughout the building site at 158 Front Street East:

Window installation is on the 21st Floors on both the East and West towers.

The East and West tower roof mechanical equipment have been hoisted into place and are currently being installed.

Finishing trades are working their way up the building: with drywall work now on 13th Floor; electricians roughing in suites on Floors 16 and 17; and plumbing rough-ins are now at Floor 15.

Elevator installers have begun their work on site and are currently installing rails in the elevator shafts.

Landscaping contractors have begun their work on the terraces throughout the building.

For details on the crane removal scheduled for Friday July 9 through Sunday July 11 please click here.