Construction Update for 158 Front Street East, June 4, 2021

There will be a regular program of work on site this Saturday, June 5: housekeeping tasks, window installation and interior suite work.

Window installation is continuing up the face of the building, work is currently on the 20th floor.

The roof on the east tower is scheduled to be completed the middle of next week. Work on the mechanical catwalk will commence shortly after the east tower roof is complete. 