This Saturday, May 22, there will be a forming contractor on site in the morning opening up wall forms that are being poured today, Friday, May 21. We expect there will be minimal disturbance and this work should be completed by approximately 10 am.
Exterior architectural fins have been installed on the lower portion of the North face of the West tower and work will commence next week on the West face of the West tower.
Simultaneously on the East tower installation of the finished metal panels and the installation of windows, via swing stage, is underway.
Looking Ahead
Concrete work for the remaining walls and the roof of the East tower is expected to be completed in the next two weeks. The cranes will remain on site to hoist material up to the terraces as work progresses into June.