The construction team plans to pour concrete for the first portion of the East tower Mechanical Penthouse slab today, weather permitting. Window installation is currently on the 16th Floor. 12th Floor suites are currently being framed while appliances, tile and countertop finishing trades currently working on the lower floors of the podium. The indoor amenity areas have been framed and are currently being dry walled.
We will have an update later in the week regarding plans for Saturday work and look ahead on upcoming construction milestones.