Construction progress has been steady at the St. Lawrence Condominiums this week. Window installation is currently active on the 15th Floor, while exterior caulking via swing stage is ongoing on the northwest face of the podium (Levels 8 through 13). Interior suite progress; kitchen cabinets are currently being installed on the 2nd Floor, appliances for this floor have also been delivered with installation scheduled to begin soon.
Saturday, April 10
There will be work crews on site this Saturday conducting housekeeping and window installation.
Next Week
The construction managers anticipate pouring the next portion of slab floor early next week, either on Monday or Tuesday. Given a large slab pour, we expect there will be late evening concrete finishing work. We will post an update when the schedule of the slab pour is confirmed.
