Construction Update: Late work Wednesday & look ahead to the weekend.

Today crews have poured the 24th Floor West tower slab. Following the wrap up of the pouring this afternoon, concrete finishers will be on-site working late. Crane lights will remain on to safely illuminate the work area until the finishing crew has completed their work. 

Installers are currently putting in windows on the 12th Floor. Interior work is ongoing through the lower and middle podium floors with finishing trades working on the 6th and 7th Floors.

Saturday, February 27th

Currently the plan for Saturday, February 27 is that there will be crews on the site. They will be opening up used wall forms, with some light crane work to remove them from the current top working floors. As per usual, there will also be workers conducting regular housekeeping, work and continued window installation.