Construction Update for Thursday, February 11, 2021

Construction crews were only able to partially complete the 23rd floor East Tower slab yesterday. Today, February 11th, the remaining concrete slab will be poured and concrete finishers will of necessity work into the later part of the day, and the evening. Crane mounted lights will remain on until the work is safely completed.

Friday, February 12th is set to be a mix of forming, interior work and possibly some column and wall pouring, depending on weather conditions.

Saturday February, 13th

We do not have specific details of the work planned for Saturday yet. However, there will be a crew on site. We will post specific details if the work plan includes more than standard mix of Saturday work, i.e. general housekeeping, interior work, and taking apart used forming structures.