Midweek Construction Update

The construction team anticipates they will be pouring a portion of the 23rd Floor East tower concrete slab this Friday, February 5th. So we anticipate that concrete finishing will go into the evening, with crane lighting remaining on until the work is safely completed.

Sections of the cantilevered East side are being formed this week. While on the West tower, walls and columns are currently being formed and poured on the 23rd Floor.

On the interior 4th Floor suites are currently being worked on. On the 6th Floor electrical and mechanical rough in continues.

While we cannot confirm the details of planned work for Saturday, February 6th, we expect that there will be site work in keeping with past weeks.