The concrete slab pour for the 22nd floor of the east tower is set for tomorrow, Tuesday, January 12.
We expect concrete pouring to be complete by the afternoon. Concrete finishing will continue into the evening, possibly as late as 11 pm.
During the evening work, the crane lights will remain on to ensure safety. The finishing crew will shut off these lights when their work is complete.
The next major concrete slab pour is expected to occur next Monday, January 18.