Updated: The concrete pour that had been rescheduled once already from Wednesday, January 6 to Thursday, January 7, has been postponed again to Friday, January 8. The concrete slab pour for the 22nd Floor west tower slab that will be poured starting this morning, Friday, January 8.
Please note concrete finishers will be working to complete the work into the late evening. The crane lights will have to remain on until the work is completed.
We’ll have update by Friday, on planned work for the weekend and look ahead to next week.