Saturday and Next Week – Construction at 158 Front St. E.


At the close of this week, exterior construction has reached the 21st Floor on both the east and west towers. Window installation has reached the 9th Floor of the podium. On the interior, finishing tradespeople continue work on the podium floors.

Saturday, December 19

Work crews will be on site tomorrow, Saturday December 19, conducting housekeeping and light work throughout the site, no crane work is expected to be conducted tomorrow.

Monday, December 21

The next major concrete slab pour will be on Monday December 21st — there will be concrete finishers working late on Monday night and by necessity the crane lights will be on until the work is complete.

We will have an update next week on the Holiday Work Schedule.