Reminder: late concrete finishing tonight at 158 Front Street East.

The concrete slab pour for the West Tower’s 21st floor has been underway today. Concrete finishing will continue through tonight. During the concrete finishing work the crane lights will remain on for safety reasons.

The finishing crew will turn off the lights once work has been completed.

The next major concrete slab pour is scheduled for next week on Monday or Tuesday. We will have an update on Friday. Next week we will also post the Holiday Work schedule.