This week the 18th Floor East tower floor slab was completed. Window installation continues to progress along the 8th Floor facade. Interior work is ongoing on the podium floors with in-suite framing and rough-ins of suite layouts.
Saturday, November 14
This Saturday there will be a similar program to last week. A trailer will be on site that will be loaded by crane with material for removal. There will also be some carpentry work and general site housekeeping through the early afternoon.
Outlook for the Week of November 16
Work will continue on the 19th Floors of the East and West towers. When the columns and walls on each of theses floors are formed and poured, the next set of slab floors will be poured. When slabs are poured there will be concrete finishing continuing into the evening,
We will have more details in our next update on Tuesday, November 17,