Construction Update for St. Lawrence Condominiums, November 5, 2020

Construction activity has reached the 18th Floor on the west tower slab, which is currently being formed in advance of concrete pouring. On the east tower the 17th Floor concrete slab is now complete. Vertical walls and columns that rise to the 18th Floor are currently being formed on the east tower.

Window installation is ongoing on the 8th Floor. Carpenters are forming the 18th Floor west tower slab.

Inside the podium, framers are currently working on 4th floor suites. Carpenters are forming the 7th Floor theatre room elevated seating area; and while mechanical tradespeople are roughing in the sanitary pipe to the 11th Floor.

Friday, November 6:

The construction team plans to pour the 18th Floor west tower slab tomorrow, Friday. There will be concrete finishers working late tomorrow evening.

There will also be workers using a swing stage on Friday, working along the south Front Street face of the podium.

Saturday, November 7

Crews will be on site this Saturday, November 7, conducting material cleanup with trucks coming into site to pick up material to be loaded by crane.

We will post and circulate an update next week.