The construction team was pouring the 17th Floor West tower slab today. They do not anticipate that concrete finishers will be working past 7pm, as long as the weather cooperates.
On Friday, October 23, the crew will be pouring 17th Floor slab on the East tower. They do anticipate that concrete finishers will be working late into the evening on Friday due to the complexities of the pour.
Window installation is currently underway on the 8th Floor, while the installation of the metal picture frame panels is underway on the 9th Floor. It is expected this round of window work will be completed by the end of the week.
The ‘rough-in’ stage is underway in the 2nd Floor suites. Other interior work is progressing with insulators and metal stud work throughout the podium floors. This will be followed by electricians and plumbers and the loading in of material, delivered via the hoists, to support their work.
We don’t have a read on Saturday work (October 24) but we will post an update by Friday, please check back then.