The mobile crane that is on-site today to work on the eastern hoist installation and occupying the north westbound lane of Front Street East was expected to be in operation on a different day, unfortunately arrangements for its use were last minute and we apologize for the lack of advance notice. It is fully permitted, site staff and a paid-duty officer are on-site. It is expected to be in use until approximately 7 pm tonight.

This week has seen the completion of the 15th floor slab, walls and columns on the west tower, and the pouring of the slab for the 16th floor. On the east tower work is underway on the 15th floor.


Work on the interior of the building is focused on drywall for the 2nd floor suites, with work also underway in the 3rd floor, the corridors on the 4th floor and the 5th floor.

Saturday, October 10

We expect that there will be staff on site this Saturday, doing housekeeping work and preparing for next week’s concrete work.

Next week highlights:

The next set of windows for 8th floor is expected to arrive on Tuesday, October 13, with installation work following.

The next major slab floor pour is scheduled for on Wednesday, October 15, and we expect that concrete finishing may extend into the late afternoon or early evening.