158 Front Street East Construction Update, October 2, 2020

All the the concrete and form work on the podium levels of the St. Lawrence Condominiums at 158 Front Street East is now complete. The construction team has begun building the two separate towers that rise from the podium.

This week, work crews have been working on the 15th Floor. The concrete for the slab floor and walls of the west tower of the 15th Floor were completed earlier this week. Today, Friday, October 2, there will be a concrete slab pour for the 15th Floor east tower. We expect that concrete finishers will be working late into the evening.

Drywall installation on the 2nd floor got underway last week and is ongoing till complete. Windows are currently complete up to the 6th Floor with installation on the 7th currently in progress, and continuing through next week.

Saturday, October 3

The construction team will be on site this Saturday, October 3. Crews will be moving wall forms into position as well as forming the 16th Floor deck.

Look Ahead

Concrete work will begin next week on the 16th Floor, as 15th Floor work is completed. We expect drywall work will move to the 3rd Floor and window installation will move to the 8th Floor.