Tomorrow, Saturday, September 26, we expect there will be workers on site conducting light work and cleaning.
As we noted in our last update, work has begun on the secondary hoist installation (external construction elevator) along Front Street. This work will continue through next week.
In a key milestone concrete work was completed for the final floor of the podium– the 14th Floor. Concrete work is underway on the initial stages of the the 15th Floor, which is the first floor of the West tower section. The first slab pour for the 15th floor was completed this week. Framing and drywall work is continuing on the lower floors of the podium units.