Progress has been steady this week on the 14th floor of the building. Interior work has focussed corridor framing throughout the lower podium levels, with work now set to move to the 4th and 5th floors. Window installation will be progressing to the 7th floor.
Saturday, September 19
This Saturday there will be a crew of 18 forming workers on site. They will be working on the forming decking for the 15th floor. This work will commence in the morning and continue through the early afternoon, no later than 3:00 pm. There will be a few workers as well throughout the building conducting miscellaneous work.
Look Ahead, Week of September 21
Next week will see concrete work continue on the 14th floor, with the focus being pouring additional concrete sections of the pool, mid week. The construction team is also projecting that concrete will be poured for the 15th floor slab on the west side of the building (closer to Frederick Street) towards the end of next week.
Window installation will continue next week on the 7th floor; as will interior corridor framing on the 4th and 5th floors.
Also next week, the installation of a second construction hoist (external elevator) will get underway on the eastern section of the building, facing Front Street East. This is a multi-step process that will continue through the next two weeks, approximately.