Construction Update, September 3, 2020

Crews on the site of the St. Lawrence Condominiums have essentially completed the precast brick cladding on the podium levels of the buildings.

Forming and concrete work is ongoing on the 14th floor of the building.

Interior suite work continues on the lower levels of the building.

Window installation has reached the 5th floor, and the ‘picture frame’ installation on the window frames is ongoing throughout the podium levels.

It is the holiday weekend so based on past practice we do not expect there to be crews on the site this Saturday, September 5. However, we will confirm this by close of business tomorrow and post and circulate a notice if there will be work this weekend.

Work will resume this Tuesday, September 8.

Have a happy and safe holiday weekend. Keep social distancing and please wear a mask.