This Saturday, August 29, there will be precast brick installation until mid afternoon. There will also be a small crew working insulation and caulking in the podium levels of the building.
Monday will see work resume on forming on the 14th floor and some concrete work is expected. There may also be additional precast exterior installation depending the amount of work accomplished on Saturday.
We will have a further update on Tuesday.