Crews will be on site this Saturday, August 22, installing precast panels on the podium levels. The crane will be in use to lift the pre-cast panels into lace. There will also be workers conducting house cleaning on the current upper level of the building.
This week, window installations has reached 4th Floor. Picture frame metal panels have reached the 6th Floor.
On the top of the building, structural formwork has begun on the 14th Floor, the outdoor amenity level which will have the base level of the outdoor patio and the pool floor.
We will post our next update on Monday afternoon, August 24.