Saturday work at 158 Front Street East, August 8, 2020

There will be crews on site on Saturday, August 8, working through the afternoon. They will be preparing “table forms” – flat wooden forms for next week’s concrete pours. These will be prepped and “flown up” – lifted by crane – the the current working area on the 13th floor.

This past week saw significant progress on the 13th floor, more window glazing installed, and additional pre-cast brick cladding installed to the exterior of the podium.

We will post and circulate a summary of next week’s work on Monday morning, prior to 7 am.

Have a safe and happy weekend.