This Saturday, August 29, there will be precast brick installation until mid afternoon. There will also be a small crew[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
This Saturday, August 29, there will be precast brick installation until mid afternoon. There will also be a small crew[…]
Read morePrecast brick installation on the podium exterior has almost completed on site. The construction management team anticipates this key piece[…]
Read moreA quick look at the podium of the St. Lawrence Condominium reveals that the installation of the pre-cast brick exterior[…]
Read moreCrews will be on site this Saturday, August 22, installing precast panels on the podium levels. The crane will be[…]
Read moreThere will be crews on-site Saturday, August 15 doing setup and housekeeping work. Concrete is now 75% complete on the[…]
Read moreThis week window installation will continue on the 3rd Floor with windows expected to begin being installed on the 4th Floor. Concrete[…]
Read moreThere will be crews on site on Saturday, August 8, working through the afternoon. They will be preparing “table forms”[…]
Read moreThis week at 158 Front Street East, concrete wall forming and pouring for the last walls on the 12th floor is[…]
Read more