There will be work on site this Saturday, July 25, 2020 from 9 am to 1 pm. Crews will be on-site doing general housekeeping and preparation work for next week’s concrete pours.
This week the 11th floor was completed and the 12th floor slab got underway with the pouring and forming of concrete.
Columns rising from the 12th to the 13th floor were also begun. More windows on the 2nd and 3rd floors were also installed this past week.
Look Ahead for the week of July 27
The last section of the 12th floor concrete slab floor is scheduled to be completed by mid -week. We expect early to mid-evening concrete finishing to accompany this final pour for the 12th floor.
Window installation will continue to progress on the 3rd floor through the week
The installation of the precast brick cladding will resume on Wednesday, July 29.
If there are significant changes to the schedule and site activities we will post an update during the week.