Weekend Construction Update for 158 Front St. E., July 17, 2020

Today at 158 Front Street East, the first concrete pour for the initial section of the 12th floor slab is underway.  This week has seen window installation progressing from 2nd to 3rd floor.

There will be crews on site tomorrow, Saturday, July 18, from 9 am into the early afternoon, doing general site housekeeping work and preparation for next week’s concrete pours.

A note on evening concrete finishing:

It may be necessary for concrete finishing to go past 7:00 pm but as it’s a challenge to predict precisely. Once crews pour the slab floor, the freshly poured concrete requires time to cure: temperature, for example, plays a role how long this takes. Once cured, concrete finishing can begin, which takes a few hours to complete. Every effort is made to finish work as early as possible.