Steady progress is being made on the St. Lawrence Condominiums. The 10th floor is complete and the 11th floor is halfway to completion.

There will be crews on site tomorrow, Saturday, June 27, doing general housekeeping work on site and taking apart wooden forming units. However, there will be no crane work and no concrete work.

Window installation has commenced on the lower levels with interior rough-in work for individual suits is set to follow, once the glazing is up on the relevant section of the building.