Work crews at 158 Front Street East made steady progress this past week building our the 10th Floor fo the St.[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
Work crews at 158 Front Street East made steady progress this past week building our the 10th Floor fo the St.[…]
Read moreWork this week will continue to be focussed on the 10th floor. Forming, pouring slab floor sections, as well as[…]
Read moreThere is no work scheduled for this Saturday, May 23, 2020. This past week significant progress has been made on[…]
Read moreDespite the less than desirable weather, progress continued this week through Friday, May 15. Work commenced today on the next[…]
Read moreToday, May 8, saw the first section of the 10th floor concrete slab floor poured. Following the pour, concrete finishers will[…]
Read moreThere will be no work on the St. Lawrence Condominiums site at 158 Front Street East, this Saturday, May 2. […]
Read more