Construction outlook for the week of April 27, 2020

The construction team is currently working on completing the 9th floor. They hope to pour last piece of the 9th floor slab by the middle of the week. 

Also next week the cranes will begin flying deck panels up for preparation for 10th floor layout. 

And starting on the morning of April 27 the hoist (external construction elevator) should up and running.

No work is scheduled for this or next Saturday (April 24 and May 2). We will post updates if this changes.  

* * *

We also note that work is progressing at a slower than normal pace due to limits on the number of workers on-site at a given time and due to ongoing physical distancing practices.