Construction Update and Look Ahead for 158 Front Street East, April 9, 2020

Regular activities are continuing on site at 158 Front Street East. However, the pace of work has been reduced in order to maintain the 2-metre physical distance clearance between workers/ trades. The site will be closed for Good Friday and re-open on Monday. There will be no Saturday work scheduled this week and next week.

The installation of the precast brick cladding has now commenced on the east side of the podium and will continue through the coming week.  Precast has reached the top of the existing floors on the west side of the building facing Front Street and Frederick Street.

Crews are currently laying decking and installing rebar on the 9th floor in preparation for the next concrete slab pour expected to commence in mid next week. 

Work hours for the site will remain 7 am to 4 pm, with the exception of precast installation and/or concrete slab pours. Both of these activities may continue past 4 pm if necessary. Noting that concrete finishing, after slab pours, may continue past 7 pm if absolutely necessary.

Leave a Reply

Your email address will not be published. Required fields are marked *