Despite recent weather conditions, high winds and cold temperatures, work has progressed steadily this past week on the St. Lawrence[…]
Read more
Construction information for 158 Front Street East
This site provides construction information and updates for the St. Lawrence Condominium project at 158 Front Street East, developed by Cityzen and Fernbrook Homes.
Despite recent weather conditions, high winds and cold temperatures, work has progressed steadily this past week on the St. Lawrence[…]
Read moreSaturday, February 21, 2020 Crews will be on site on Saturday doing general housekeeping tasks on site and taking apart[…]
Read moreThis week cladding on the lower floors has begun to be visible. The cladding is pre-cast with brick facing. Prior[…]
Read moreWe expect there will likely be a crew on site this Saturday, February 8. They will be taking apart concrete[…]
Read moreWork is progressing on site to set up the hoist–external construction elevator–at the west side of the building, facing Front[…]
Read more