Saturday Work & Look Ahead for 158 Front St. East.

Crews will be on site tomorrow, Saturday, November 23 from 9 am. They will be taking apart forms form already finished concrete and doing a variety of key housekeeping tasks on-site.

Public Art in progress

The public art on the hoardings is moving ahead. Painting on the southwest section of the hoardings is completed.  Artist Erin McCluskey and her team will work on the southeast corner of the site next. These are the two sections of the hoarding and fencing that will feature artwork.

The 5th Floor in progress on November 21, 2019

Looking Ahead

Next week work will continue on the 5th, 4th, and 3rd floors across the site. We expect there to be daily concrete pours, weather permitting from Monday to Friday. Concrete finishing may extend past 7 pm as required.

Concrete will be delivered to the site via Frederick Street to the service lane at the north side of the building.

REVISED: We will provide our next scheduled update on Thursday, November 28. Please check back regularly for updates.